Journal article
Pressure Drop Optimization of the Main Steam and Reheat Steam System of a 1000 MW Secondary Reheat Unit
Abstract
The pressure drop of a main steam and reheat steam system should be optimized during the design and operation of a thermal power plant to minimize operation costs. In this study, the pressure drop of the main steam pipe and reheat steam pipe of a 1000 MW secondary reheat unit are optimized by modulating the operation parameters and the cost of operation is explored. Optimal pipe specifications were achieved by selecting a bend pipe and …
Authors
Li Y; Liu J; Huang G
Journal
Energies, Vol. 15, No. 9,
Publisher
MDPI
DOI
10.3390/en15093279
ISSN
1996-1073